30-Second Read

In one line. Cushman & Wakefield expects about 55,600 Dubai homes to complete in 2026, the most since 2008, while Savills counts roughly 50,000 launches in nine months, 64% fewer than a year earlier (Khaleej Times, August and October 2026).

Best for. Investors weighing resale and rental risk in communities with heavy handovers, and off-plan buyers checking delivery dates.

What you will learn.

  • How many homes complete in 2026 and 2027
  • Why two forecasts give different totals
  • How far launches have fallen
  • What a 525,000-unit pipeline really means

Bottom line. Supply is arriving now, and new launches have dropped sharply. The pipeline on paper is far larger than what construction can deliver on time.

Completions Peak in 2026

Cushman & Wakefield Core forecasts about 55,600 deliveries in 2026, the highest annual total since 2008, and more than 60,000 in 2027.

The split. The firm counts more than 13,218 homes delivered in Q2 and expects about 32,000 in the second half. Q2 handovers included Crest Grande in Sobha Hartland (965 apartments) and Malta 1 in Damac Lagoons (760 units).

Savills sees more. Savills expects 50,000 to 60,000 handovers in the second half and 75,000 to 85,000 for the full year, with the rest slipping into 2027. It counted about 26,500 in the first half, around 85% of them apartments.

Why the gap. The two firms publish different totals for 2026 (55,600 against 75,000-85,000). The articles do not explain the difference, so treat both as ranges and not as a single number.

2026 handover forecasts
Source2026 totalNote
Cushman & Wakefield Core (H1 report)About 55,600About 32,000 expected in H2
Savills (Q3 report)75,000-85,000Remainder likely to slip into 2027

Launches Have Slowed

Apartment launches fell about 58% and villa launches about 78% in H1 2026 compared with H1 2025 (Cushman & Wakefield Core).

Q3. Savills counts about 5,000 launches in Q3. For the first nine months it counts about 50,000, which is roughly 64% below the 137,300 launched in the same period of 2025.

What launched. The firm notes that projects which did go ahead were mainly mid-market and end-user homes. Developers deferred launches in Q2 as geopolitical uncertainty rose.

Incentives. To support sales, developers are using payment plan changes, DLD fee waivers, bulk discounts and higher broker commissions, according to the same report.

The 525,000-Unit Pipeline

Savills counts more than 525,000 units scheduled for delivery between 2027 and 2030. Only about 186,000 have passed 20% construction progress (Cushman & Wakefield Core).

Read the progress number. A unit with a handover date is not a unit under construction. The Cushman & Wakefield report expects actual completions to fall well short of scheduled targets because of supply chain limits, contractor capacity and softer market conditions.

The June view. Fortune reported in June that about 65,000 apartments and 12,500 villas were scheduled for delivery by year-end, with many expected to slip into 2027. Moody's warned that a sharp drop in population inflows would raise absorption risk as completed supply grows.

The support. Cushman & Wakefield expects the launch slowdown to balance the pipeline and improve take-up over the medium term. Savills says population and household growth will matter more than launch counts in absorbing supply.

What It Means for Investors

Handover-heavy communities carry the most near-term rent and resale pressure.
  • Look at the handover calendar. If your building shares a community with several large completions this year, expect more competing listings.
  • Ask your developer for a dated progress report. The 186,000-unit figure shows that scheduled and started are different things.
  • Expect incentives to continue. Fee waivers and payment plan changes are the tools developers are using now. Compare offers on total cost, not headline discount.
  • Use the Off-Plan Map. The YAZDAN Off-Plan Map shows current projects by area, which helps you see how many launches sit near the one you are considering.

"A handover date is a plan. A construction milestone is a fact. Buyers should ask for the second one."

YAZDAN Research

Buying near a heavy handover zone?

We map completions, launches and competing listings around the building you are considering.

Book a 30-minute advisory call →

Frequently Asked Questions

How many homes will Dubai complete in 2026?

Cushman & Wakefield Core forecasts about 55,600. Savills forecasts 75,000 to 85,000. The two firms' totals differ, and the articles do not give the reason.

Have new launches dropped?

Yes. Savills counts roughly 50,000 launches in the first nine months, about 64% below the 137,300 in the same period of 2025.

How much of the pipeline is actually being built?

Of nearly 525,000 planned units through 2030, about 186,000 had passed 20% construction progress, per Cushman & Wakefield Core.

Will rents fall because of new supply?

The sources describe rebalancing, with uneven rent movement by community. Savills reports falls of up to 15% in some communities and almost none in others.

Should I avoid buying now?

That depends on the building and the price. Check handover volume nearby, the developer's progress and rents in the same community before you commit.

Sources cited in this article

Editorial analysis for information only, not financial advice. Figures as reported by cited sources; verify current rules and unit-level details via DLD before any decision.

The YAZDAN app
Get AYAN, YAZDAN's free property app

A live off-plan map of 1,700+ UAE projects, a full UAE mortgage calculator and OS-level spam-call protection, all in one app.

Get the AYAN app →

Or go straight to the App Store or Google Play. On a computer? Open map.YAZDAN in your browser, no download needed.

AYAN app by YAZDAN: off-plan map, mortgage calculator and spam-call protection