The short answer

Dubai law gives off-plan buyers a full refund in two cases: when RERA cancels the project by a final, reasoned decision, and when the developer never started work for reasons outside its control (Article 11(b) of Law No. 13 of 2008, as amended by Law No. 19 of 2020). For an ordinary delay, the law sets no fixed compensation. Your rights come from the delay and termination clauses in your sale agreement, and claims over stalled or cancelled projects go to a special tribunal set up under Decree No. 33 of 2020.

Best for. Off-plan buyers whose project is late or stalled, and anyone about to sign a sale and purchase agreement (SPA).

What you'll learn.

  • The laws that protect off-plan buyers
  • When you're owed a full refund
  • What you can do about a late project
  • What happens if you stop paying

Bottom line. Read the completion date, grace period and delay clauses before you sign. Once a project is late, they're the main rules you have.

The laws that apply

LawWhat it does for buyers
Law No. 13 of 2008 (Interim Real Property Register)Off-plan sales must be entered on the interim register, known as Oqood, or they're void (Article 3). A developer can't sell before it has the land and approvals (Article 4). If a unit turns out smaller than agreed, the developer must compensate the buyer unless the difference is minor (Article 12).
Article 11, rewritten in 2009, 2017 and 2020Sets what happens when a buyer stops paying and when a project is cancelled. The current text comes from Law No. 19 of 2020.
Law No. 8 of 2007 (escrow)Buyers' payments go into a project escrow account. If a project stops in an emergency, the escrow bank, after consulting DLD, must see it completed or refund buyers (Article 15).
Decree No. 33 of 2020Runs a special tribunal for unfinished and cancelled projects.

Sources: Dubai Legislation Portal.

For how escrow works and its limits, see Off-plan escrow law (Law No. 8 of 2007).

When you get a full refund

  • RERA cancels the project. If RERA cancels a project by a final, reasoned decision, the developer must refund everything buyers paid, in line with the escrow law (Article 11(b)).
  • Work never started. If the developer didn't start work for reasons outside its control, and not through its own negligence, it must also refund everything. Until the 2020 amendment it could keep up to 30%.
  • The project stops in an emergency. The escrow bank must act to protect depositors, either by getting the project finished or by refunding them (Article 15 of Law No. 8 of 2007).

The refund covers money paid to the developer. If you bought from another buyer, the premium you paid them didn't go into escrow.

If your project is late

  1. Read your SPA. Check the expected completion date, any grace period, and whether it gives you compensation or a right to cancel after a set delay. Law No. 13 of 2008 doesn't give buyers an automatic right to cancel for delay, so the contract matters most.
  2. Check progress. Follow the project through DLD's services, such as the Dubai REST app.
  3. Write to the developer. Ask for a revised date and keep every reply.
  4. Complain about violations. DLD's complaint service handles breaches of the rules by real estate companies, with a target reply time of five working days. It doesn't handle money claims, contract disagreements, cancellations or compensation, or transactions older than six months.
  5. Go to court or arbitration. Article 11(g) keeps buyers' right to go to court or arbitration. Your SPA may say which one applies.
  6. Stalled or cancelled projects. Claims about projects proven unfinished, or cancelled under Law No. 13 of 2008, go to the special tribunal. Other courts, including the DIFC Courts, can't hear them.

The special tribunal for unfinished and cancelled projects

Decree No. 33 of 2020 took over the committee first set up in 2013 and renamed it the Special Tribunal for Unfinished and Cancelled Real Property Projects. It sits at DLD and covers Dubai projects outside the DIFC.

  • It hears claims about unfinished projects, including those RERA refers to it, and can hand a project to another developer to complete.
  • It liquidates cancelled projects and settles buyers' and investors' rights after liquidation costs.
  • Its decisions are final and are enforced by the Execution Court at Dubai Courts.

If you're the one who stops paying

A developer can't simply cancel and keep your money. It has to report the default to DLD, which gives you 30 days' written notice and may try to broker a settlement. If you still don't pay, DLD certifies how far the whole project has progressed, and that sets the developer's options:

  • Over 80% complete: keep the contract and claim the balance, ask DLD to auction the unit, or cancel and keep up to 40% of the unit price.
  • 60% to 80%: cancel and keep up to 40% of the unit price.
  • Under 60%, with work started: cancel and keep up to 25% of the unit price.

The rest must be refunded within a year of cancellation, or within 60 days of a resale, whichever comes first. Since 2020 the test is the progress of the whole project, not just your unit.

Common questions

Can I cancel my off-plan purchase because the project is late?

Not automatically. Dubai's off-plan law doesn't give buyers a cancellation right for delay. You can cancel if your SPA allows it after a set delay, if the developer agrees, or if a court, arbitrator or the special tribunal orders it.

What happens to my money if RERA cancels the project?

The developer must refund everything you paid, in line with the escrow law. The special tribunal handles the liquidation of cancelled projects and settles buyers' rights.

How much can a developer keep if I stop paying?

After DLD's 30-day notice, up to 40% of the unit price if the project is over 60% complete, or up to 25% if it's below 60% and work has started. The rest must be refunded.

Can RERA order a developer to pay me compensation for delay?

No. DLD's complaint service doesn't handle money claims, contract disputes or compensation. Those go to court, to arbitration if your SPA requires it, or to the special tribunal for unfinished and cancelled projects.

Sources
  1. Law No. (13) of 2008 Regulating the Interim Real Property Register, Dubai Legislation Portal
  2. Law No. (9) of 2009 Amending Law No. (13) of 2008, Dubai Legislation Portal
  3. Law No. (19) of 2017 Amending Law No. (13) of 2008 Regulating the Interim Real Property Register, Dubai Legislation Portal
  4. Law No. (19) of 2020 Amending Law No. (13) of 2008, Dubai Legislation Portal
  5. Law No. (8) of 2007 Concerning Escrow Accounts for Real Estate Development, Dubai Legislation Portal
  6. Decree No. (33) of 2020 Concerning the Special Tribunal for Unfinished and Cancelled Real Property Projects, Dubai Legislation Portal
  7. Dubai Land Department: Complaint Against a Real Estate Company
  8. Al Tamimi & Company: Dubai amends interim registration law (2021)

The Arabic text of Dubai legislation prevails over English translations.

Want a tailored read for your own position?

30 minutes with our advisory team: we read the DLD numbers for your goal, whether you are buying, selling or investing, and tell you plainly what they mean.

Book a 30-minute advisory call →
The YAZDAN app
Get AYAN, YAZDAN's free property app

A live off-plan map of 1,700+ UAE projects, a full UAE mortgage calculator and OS-level spam-call protection, all in one app.

Get the AYAN app →

Or go straight to the App Store or Google Play. On a computer? Open map.YAZDAN in your browser, no download needed.

AYAN app by YAZDAN: off-plan map, mortgage calculator and spam-call protection